We created header information and some base data at lines: Construction Positions. Unit of Measures and Quantities. We can put one of unit of measures, we configured on Construction Position. If we have Quote Requirement in Excel from customer with many Position lines, we can use command ‘Import from Excel’ from ribbon. After that we can start with calculation of Position Price for quote.
For calculation process, we start the command ‘Calculate process and costs’ from ribbon. We can choose next options:
- Price List: NAV will use Price List from Construction Position defined for this project (I describe Construction Position Price List in my old post)
- Calculation: we need to fill percent of ‘Planned Margin’ and NAV will add this percent on calculated Unit Price at BoQ line
When we first time start this command, we must to mark field ‘Calculate normatives’. NAV will be use active version of normative for this construction position with planned resource and item consumption (or subcontract work) to calculate unit cost of construction position and unit price of construction position.
If we some other time start the same command, we need to:
- Mark ‘Calculate normatives’ if we want use other version of normatives,
- Unmark ‘Calculate normatives’ if we only want change percent of ‘Planned Margin’.
NAV will calculate all amounts and will link used version of normatives to BoQ line.
We can change ‘Unit Position Price with Discount’ directly from field or adding value in ‘Discount %’ field. NAV will use next calculation method:
Will be continue…