What is a main difference between using Output Order and Job & Position Journals?
As I wrote in my first post for this theme, we can post the operational work on next ways:
- Using ‘Output Order’– posting of Construction Position output work and Resource and Item consumption per Project in the same time;
- Using ‘Position Journal’– posting only Construction Position output work per Project; we need to post consumption separately;
- Using ‘Job Journal’ (standard NAV functionality with some specific customizations) – posting only Resource and Item consumption per Project; we need to post output separately;
Advantage of the first method is that we can post all entries with the one document. We get posted document with ‘Navigate’ functionality. Also, this method enables us to have complete statistic of cost per every Construction Position for each Project.
As we look up in Construction Position Statistic for position posted using Output Orders, we can see Using (position cost), Sales (position revenue) and Profit:
On previous picture we see position cost for each period.
In previous example, I presented Construction Position Statistic from NAV, and this is shown only costs, revenue and profit, without analytics. Also, if we use Output Orders for posting, we can make deeper analysis with complete analytics of resources and items cost or quantities, as picture bellow (from BI4CONS):
Failing of this method is that if we have many complex position works per day, it is too complicated to make evidence and post it.
If we choose posting without ‘Output Order’, we get simply procedure for posting. We use ‘Position Journal’ for evidence of work per all Construction Position we have and separately we use ‘Job Journal’ for evidence of consumption all Items and Resources, not linked with Construction Positions. On this way we get simpler method, but we lose connection of consumption with Construction Position output. Using this method of posting, we know revenue for each position on project, but we don’t know position cost and profit. We could know cost and profit only per complete project or combination project and project task, and of course we will know this data per required period. As we look up in Construction Position Statistic for position posted using Position and Job Journals, we can see only Using (quantity, not a position cost) and Sales (position revenue):
On previous picture, we cannot see position cost.
Position sales data (previous picture) are the same as when we use Output Orders. But when we try to see profit, we will get a wrong data with 100% margins.
We cannot get all things and we must to decide what method we want. Good thing is that we can choose different method for each project, depend of complexity and project requirement. Good thing is also that we can set filter on Position Statistic and we can see complete data for position posted using Output Order on each project.