Hi All,
Give your valuable comments on following scenario,
Scenario: - Finish good item A
Item | Status | BOM no | Route no | SKU exsit |
A | Finish good | BOM-A | Route-A | Yes.( WIP-->production) FG-store--> transfer from WIP) |
B | BOM item of A | BOM-B | Route-B | Yes(WIP-->Production) |
C | BOM of item B | BOM-C | Route-C | Yes(WIP-->Production) |
D | BOM of item C | BOM-D | Route-C | Yes (WIP-->Production) |
Released Sales order with 100 Qty. of item A. (order date & shipment date equal to 18/09/2013)
- Run planning worksheet (PW) with the start date equal to (18/09/2013)
- Result;
Item No | Due date | Start date & time | End date & time | Order No |
A | 09/18/13 | 09/17/13 11:39:57.997 PM | 09/18/13 07:59:59 AM | Order No 1 |
B | 09/17/13 | 09/14/13 05:28:55.997 PM | 09/17/13 07:59:59 AM | Order No 2 |
C | 09/17/13 | 09/16/13 04:29:57.997 PM | 09/17/13 07:59:59 AM | Order No 3 |
D | 09/17/13 | 09/16/13 06:59:57.997 AM | 09/17/13 07:59:59 AM | Order No 4 |
- Normal starting time 8.00.00 AM (Manufacturing setup)
- Normal End time 7.59.59 AM (Manufacturing setup)
- Company run three work shift (8 hours for each)
- Here you can see PW it was calculated backward. Can’t we set it as forward calculation? (When run PW)
- Here I want to start the process & end the process sequentially. As an example,
- Order no 4(item D) has to start first & after it finish only order No 3 (Item C) can start.
- Then order No 2 (Item B) can start & after it finish only Order No1 ( item A) should plan
Sample plan.
Item No | Due date | Start date & time | End date & time | Order No |
A | 09/18/13 | 09/17/13 16.00 PM | 09/18/13 07:59:59 AM | Order No 1 |
B | 09/17/13 | 09/17/13 13.00 PM | 09/17/13 16.00 PM | Order No 2 |
C | 09/17/13 | 09/17/13 10.00AM | 09/17/13 13.00 PM | Order No 3 |
D | 09/17/13 | 09/16/13 7.00 PM | 09/17/13 10.00 AM | Order No 4 |
Is there are any standard function to this scenario?
Currently we customized.
Thanks in advanced.