Forum Post: RE: Planning worksheet- Dynamics NAV 2009 R2

"" Here I want to start the process & end the process sequentially. As an example,

a.       Order no 4(item D) has to start first & after it finish only order No 3 (Item C) can start.

b.      Then order No 2 (Item B) can start & after it finish only Order No1 ( item A) should plan  ""

Above  part is no need to customize,

If i change the Manufacturing policy on item card or SKU card as "MTO(Make to order)"  system will calculate production order sequentially.