"" Here I want to start the process & end the process sequentially. As an example,
a. Order no 4(item D) has to start first & after it finish only order No 3 (Item C) can start.
b. Then order No 2 (Item B) can start & after it finish only Order No1 ( item A) should plan ""
Above part is no need to customize,
If i change the Manufacturing policy on item card or SKU card as "MTO(Make to order)" system will calculate production order sequentially.