What is new about future Microsoft Dynamics NAV version with codename ‘Crete’? I wrote something about ‘Crete’ here.
TAP nominated process is finished by November 15, 2013. Microsoft still not finished selection process. When I look at Connect site, I get the next screen:
That mean my status is still pending. Microsoft published plan that selection and application process will be finished in period October – November 2013. In this period, Microsoft will select candidates for program and will signature TAP Agreements.
Other plan is:
Planning and Design Review:
December 2013 – January 2014
- Early Scenario and plan input
- TAP knowledge transfer 1 (KT1)
Feature Validation:
January – May 2014
- Bi-weekly builds of NAV ‘Crete’ released
June 2014
- TAP knowledge transfer 2 (KT2)
- CTP / Go-Live Release
TAP Go-Lives and CfMD Pre-certifications:
June – August 2014
- Release for Manufacturing (RTM)
General Availability (GA)
Q3 or Q4 2014